REDUCING THE DURATION OF THE FLOW-LINE CONSTRUCTION IN PARALLEL USING EXISTING TEAMS
In this article, a matrix model (ones (rank organization of types of work matrix (ROTW)) is used to determine the location and connection in space and time of the main and additional parallel grippers. The main works are used to calculate the values of grippers by a sequential parallel method for technologically similar processes, and additional ones - by a parallel method to increase the amount of resource. The mathematical model includes the research objective and parameters that affect the construction time.