REDUCING THE DURATION OF THE FLOW-LINE CONSTRUCTION IN PARALLEL USING EXISTING TEAMS

2024;
: 32-39
https://doi.org/10.23939/jtbp2024.01.032
Received: March 02, 2024
Revised: March 15, 2024
Accepted: May 02, 2024
Authors:
1
Lviv Polytechnic National University, Department of building production

In this article, a matrix model (ones (rank organization of types of work matrix (ROTW)) is used to determine the location and connection in space and time of the main and additional parallel grippers. The main works are used to calculate the values of grippers by a sequential parallel method for technologically similar processes, and additional ones - by a parallel method to increase the amount of resource. The mathematical model includes the research objective and parameters that affect the construction time. The optimal solution is achieved by the parallel method in stages: by reducing the periods and duration of flow-lines, initial and final values of grips and critical works.  There has been no study of a sequential method of reducing the construction period using only existing crews. The effectiveness of the phased method of reducing the construction period is determined in comparison with the method of using additional parallel flow-lines

Gross J. L., Yellen J. (2006).  Graph theory and its applications. Second edition. Boca Raton-London-New York: Chapman & Hall/CRC, 2006.  https://www.taylorfrancis.com/books/mono/10.1201/9781420057140/graph-the...
Thomas H. Cormen, Charles E. Leiserson, Ronald L. Rivest, Clifford Stein. (2007). INTRODUCTION TO ALGORITHMS third edition. - Cambridge ; London . ISBN 978-0-262-03384-8
Brucker P.(2007). Scheduling. Algorithms Springer Berlin, Heidelberg, New York. 317 p.   https://ftp.idu.ac.id/wp-content/uploads/ebook/ip/BUKU%20SCHEDULING/Sche...
V. S. Tanaev, Yu. N. Sotskov, V. A. Strusevich.(1989). Scheduling theory: Multi-stage systems Science. Ch. ed. physics and mathematics lit.. - 327 p. [in Russian]. URL: https://b.eruditor.link/file/483703/
Lazarev A.A., Gafarov E.R. (2011). Scheduling theory. Problems and algorithms. Tutorial. - Lomonosov Moscow State University. - 222 p. [in Russian]. URL: https://b.eruditor.link/file/984711/
Jason Chao-Hsien Pan, Jen-Shiang Chen, Chii-Ming Chao (2002). Minimizing tardiness in a two-machine flow-shop. Computers & Operations Research, 29, 869-875. DOI: https://doi.org/10.1016/S0305-0548(00)00090-3
https://doi.org/10.1016/S0305-0548(00)00090-3
Pinedo M.L. Scheduling: Theory, Algorithms, and Systems  (2012). IOMS Dept Rm 8-59 KMC, NYU Stern School of Business, New York, USA, 669 p. DOI 10.1007/978-3-319-26580-3
Maj T. (2007). Organszacja budowy. Warszawa. URL: https://books.google.pl/books?id=jO-GGbZsFEsC&printsec=copyright&hl=pl#v....
Ushatsky S. A., Sheiko Y. P., Triger G. M. (2007). Organization of construction [in Ukranian]. URL: http://aleph.lsl.lviv.ua:8991/F/?func=direct&doc_number=000239942&local_...
Hrihorovskyi P.Ye., Bronevitskiy A.P., Murasova O.V., Hrigorovskуi A.P. (2022) Analysis of world experience and modern technical solutions for the construction of rapidly constructed residence buildings."New Technologies in Construction", № 41. P. 10-20.  [in Ukranian]. URL: DOI https://doi.org/10.32782/2664-0406.2022.41.2
https://doi.org/10.32782/2664-0406.2022.41.2
Mudryy I. (2011). Technology of the foundation with regard to functional space. (Ph. D. dissertation abstract) [in Ukranian]. URL: http://irbis-nbuv.gov.ua/cgi-bin/irbis_nbuv/cgiirbis_64.exe?Z21ID=&I21DBN
 Marcinkowski R.,   Banach M. (2020) Crane Selection Problem in Assembly Works Planning - Criteria Relevance and Methods.  Archives of Civil Engineering | Vol. 66 | No 3 | 377-390 | DOI: 10.24425/ace.2020.134403
https://doi.org/10.24425/ace.2020.134403
Ivaneiko І. D., Ivaneiko M. M. (2020). Theoretical research into shortening construction times using integrated processes. Scientific bulletin of civil engineering, 100(2). Pp. 119-126 [in Ukranian]. URL: http://nbuv.gov.ua/UJRN/Nvb_2020_100_2_21.
Shumakov I. V. (2015). Theoretical and methodological principles of the formation of organizational and technological solutions for the construction of the underground part of civil buildings (Doctoral dissertation abstract) [in Ukranian]. URL: http://aleph.lsl.lviv.ua:8991/F/?func=direct&doc_
number=000499960&local_...
Mudryy I. (2017). Procedure and principles realization of jib crane effective set formation. Management of Development of Complex Systems, 30, 156-162. [in Ukranian].URL: http://urss.knuba.edu.ua/files/zbirnyk-30/23.pdf.
Hicks S.J., Lawson R.M., Rackham J.W., & Fordham P.( 2004).  Comparative Structure Cost of Modern Commercial Buildings (Sec.Ed.) SCI P137, 85 p. https://www.steelconstruction.info/images/d/df/SCI_P137.pdf
Using modern methods of construction to build homes more quickly and efficiently: Report by National Audit Office, 2005. - 29 p.  https://webarchive.nationalarchives.gov.uk/ukgwa/20170207052351/https://...
Kelley J. E., Walker M. R. (1959) Critical-path planning and scheduling. In Papers presented at the December 1-3, 1959, eastern joint IRE-AIEE-ACM computer conference (IRE-AIEE-ACM '59 (Eastern)). Association for Computing Machinery, New York, NY, USA, 160-173. DOI: https://doi.org/10.1145/1460299.1460318
https://doi.org/10.1145/1460299.1460318
Afanasiev V. A. (1990). Flow-line organization of construction. Leningrad [in Russian]. URL: http://aleph.lsl.lviv.ua:8991/F/?func=direct&doc_number=000275862&local_...
Schaller J. (2005). Note on minimizing total tardiness in a two-machine flowshop. Computers & Operations Research. 32(12), 3273-3281. DOI: https://doi.org/10.1016/j.cor.2004.05.012.
https://doi.org/10.1016/j.cor.2004.05.012
Ivaneiko I., Oleksiv Y. (2022). Optimization of deployment periods of non-rhythmic flow-lines by complex mechanized machines, Theory and Building Practice, 4 (2), 75-82. DOI: https://doi.org/10.23939/jtbp2022.02.075.
https://doi.org/10.23939/jtbp2022.02.075
Ivaneiko I. (2023) System of redistribution of non-used resource work in non-rhythmic flow-lines. Theory and Building Practice, 5 (1), 64-71. https://doi.org/10.23939/jtbp2023.01.064
https://doi.org/10.23939/jtbp2023.01.064
Optimization of processes and costs in construction  (2023) https://www.planradar.com/ru/ebooks/optimisation-processes-and-costs-in-...